The proposed Project includes capturing LFG and combusting it in the flare. As an optional later phase, LFG may be utilized for electricity (and possibly heat) production.
The estimated capacity of LFG power engines which can be commissioned is 1.2 MW for the Yalta landfill and 0.6 MW for the Alushta landfill. The decision to invest in LFG to Energy (“LFGTE”) modules will be made on the basis of an economic review, possibility to connect to the public grid, and whether a Power Purchase Agreement (“PPA”) can be obtained.
Project applicant: C6 Capital, CCM, UK, «Gafsa» ltd, Ukraine
Expected GHG emission reductions:
GHG emission reductions for the period 2009-2012:
- Flaring: 218 th t СО2-eq/year
- Power and thermal energy displacement: 287 th t СО2-eq/year
Main parameters | LFG-to-energy | Flaring | ||
Total project cost, EUR | ? 2 033 027 | ? 781 165 | ||
Annual operation cost, (average for 2008-2020), EUR/year | ? 126 982 | ? 46 870 | ||
Financial parameters | Without ERUs | With ERUs | Without ERUs | With ERUs |
IRR, % | 2,8% | 19,9% | – | 14,2% |
NPV, EUR | ? 309 071 | ? 2 607 591 | – | ? 674 939 |
Simple payback period, years | 9,0 | 4,9 | – | 5,7 |
Current status: PDD passed determination; project received the Letter of Approval from National Environmental Investment Agency of Ukraine (NEIA).